Setting out a building: why the surveyor arrives before the excavator

An error of 30 centimetres in the position of the foundations looks trivial on paper. On site it means a building too close to the boundary, trouble with the building inspector and expensive corrections. That is why work on a plot doesn’t start with the excavator, but with the surveyor.

ContextThis article describes setting out (iskolčenje) under Serbian construction rules, in particular the Law on Planning and Construction.

What is setting out?

Setting out means transferring the designed position of a building from the drawings onto the ground. On the plot, the surveyor marks the axes and corners of the building and sets the height, i.e. the zero level. The contractor then digs the foundations and places the formwork according to those marks.

What the law says

Under the Law on Planning and Construction, before construction starts the investor must arrange for the marking of the building plot and of the regulation, levelling and building lines, in line with the regulations on surveying work. Before the works begin, the investor also files a notice of commencement with the authority that issued the building permit.

So setting out isn’t optional; it’s an obligation. On top of that, it is the cheapest insurance your building can have.

What to prepare

  • The design, with the site plan and coordinates, ideally in DWG format;
  • known plot boundaries: if the boundaries haven’t been marked, we first do boundary marking, so the distances from the boundary are correct;
  • a cleared site, free of vegetation and rubble where the building will stand.

What happens on site

  1. Checking the data. Before going on site we check that the design matches the boundaries and the situation on the ground.
  2. Marking the axes and corners of the building with pegs and marks.
  3. Offset marks outside the excavation, known as profile boards, so the axes are preserved even after the excavator has dug out the corners.
  4. A benchmark, the point from which the contractor measures all heights.
  5. A setting-out record with a sketch, as evidence that the building was marked exactly according to the design.

What comes after setting out

When the foundations are finished, the contractor files a statement that the foundations are complete, accompanied by a survey of the built foundations. That survey confirms the building is being built where it was designed. At the end of construction comes the as-built survey for the occupancy permit and registration in the cadastre.

TipIt helps if the same surveyor does the setting out, the foundation survey and the final survey. The data stays connected from the first peg to the title deed, and any deviation is spotted in time.